Three Florida associations made the news this year over big repair projects. In each case the board got ahead of the notice, the vote or the budget that owners had been given.

An Orange County HOA is accused of paying a $232,000 roofing deposit twelve days before the board voted. In Orlando, a judge stopped a condo's $2.6 million assessment because owners got ten days' notice instead of fourteen. In Fort Lauderdale, a $1.6 million concrete job has grown to about $36 million.

This guide is for the board members and managers who approve, sign and pay for a big repair project. It covers the order the law expects, how to get the notice right, how to pay without losing control of the money, and what protects you personally. A date checker tests your own dates.

This is general information for Florida boards and managers, not legal advice. Statute numbers link to the current text on the Florida Senate website. Last verified October 25, 2026.

Three stories, one pattern

Each one is a different mistake, and all three were avoidable.

Dr. Phillips, Orange County: a deposit allegedly paid twelve days before the vote

Allegation Lawsuit reported by News 6 (WKMG) on October 20, 2026. No ruling yet.

The Vistas at Phillips Commons is a 160-unit townhome HOA. Owners were asked for about $13,158 each toward a $2.1 million roofing project. According to the lawsuit, HOA records show a $232,000 deposit check to the roofer dated June 10, 2026. The board meeting to vote on the project was June 22.

Owners have sued the HOA and its management company. They say the contract was signed and the money paid without a lawful board vote under 720.303. Police will only confirm that an investigation is open. Nothing has been proven. The owner leading the lawsuit called the check "the smoking gun."

Villa Medici, Orlando: ten days' notice on a $2.6 million assessment

Court finding, as reported Orange County case 2025-CA-007724-O. Reported by FOX 35 on June 12, 2026.

A condominium board wrote to owners on July 10, 2025 about a $2.57 million special assessment. The letter said it "has been approved by the board of Directors." The envelope was postmarked July 18. The vote was July 28, ten days later. The board voted 3 to 0 and collected more than $1 million.

A circuit judge found two problems: owners did not get 14 days' notice, and the letter wrongly said the assessment was already approved. The judge stopped the collection and ordered records, minutes and an audit. Owners are now trying to remove the board. Other claims in the case are still unproven.

The Galleon, Fort Lauderdale: $1.6 million becomes $36 million

Reported CBS News Miami, October 6, 2026. Cost figures are the residents' and are not audited.

This oceanfront tower was built in 1967. Residents told CBS News Miami that a concrete restoration started about five years ago with a $1.6 million estimate. It now stands at about $36 million. Individual owners owe between $135,000 and $320,000 each.

The contractor said the association kept adding to the job through "numerous owner-approved change orders and additional contracts." A change order is a signed add-on to the contract, and each one raises the price. The reporting mentions no independent engineer on the association's side. A former board member: "We were run roughshod over, not told things, and lied to."

Dr. Phillips is about sequence. Villa Medici is about notice. The Galleon is about control after the vote.

These fights go to circuit court, not the state's cheaper arbitration program. In a 2009 appeals case, Mitchell v. Beach Club of Hallandale, an owner who said the notice was defective was allowed to sue to stop collection. HOA owners have no arbitration option either, though the HOA statute may require mediation first (720.311).

For a board, one notice mistake can put you in front of a judge, with legal bills on both sides.

Notice, meeting, vote, sign, pay

Florida law never says "vote first, sign second" in those words. But every rule it does contain assumes that order, and a board that breaks it loses its legal cover.

A board can only act at an open meeting that owners were told about in advance (a "noticed" meeting). For an HOA, a board meeting "occurs whenever a quorum of the board gathers to conduct association business" (720.303(2)(a)). A quorum is enough directors to do business, usually a majority.

For a condo, any board meeting with a quorum present is open to all owners (718.112(2)(c)). Under both laws, directors may not vote by email. A contract approved by a round of phone calls or emails, or by the president alone, is not a board decision.

Every board meeting needs posted notice 48 hours ahead that lists the agenda items, so the repair contract must be on the agenda. If a special assessment (a one-time charge on top of regular dues) pays for the project, the notice jumps to 14 days by mail plus posting.

Whatever the notice period, the vote date is the earliest day anything should be signed or paid.

Condo boards have one more rule. Under 718.112(2)(c)3, if an agenda item approves a contract, "a copy of the contract must be provided with the notice" or posted on the website or app. Owners read it before the vote. A contract signed before the meeting is a decision, not a proposal.

Signing early does not cancel the contract. If the vendor had good reason to believe the president could sign, the association is usually stuck with the deal.

What signing early destroys is the board's own protection. There is no vote in the minutes to point to. Owners can challenge the assessment. The director who acted alone may be personally on the hook. If this has already happened, see the first FAQ below.

Tool

Approval date checker

Enter the dates from your file. The checker counts the way Florida association lawyers do: the day after mailing is day one. It flags anything signed or paid before the vote. It works in whole days, so check the time of day on a 48-hour posting yourself.

These are the legal minimums. Your bylaws may require more notice, and your declaration may require the owners themselves to vote on the assessment.

Getting the 14-day notice right

Fourteen full days from the day after mailing, proven by the postmark. The notice says assessments will be considered and what for. It never says the decision is already made.

For an HOA, 720.303(2)(c)2 is blunt. If the notice does not say that assessments will be considered, and what kind, the assessment is invalid. For a special assessment, every owner gets written notice by mail, hand delivery or email at least 14 days before the meeting, and the notice is posted on the property for the same 14 days.

For a condo, 718.112(2)(c)1 requires the same 14 days plus posting for any non-emergency special assessment. The person who sent the notice signs an affidavit, a sworn statement of when and how it went out, and files it in the official records.

Under 718.112(2)(c)3 the condo notice must also give the estimated cost and say what the money is for. An agenda line that just says "Special Assessment" is not enough.

Count carefully. Becker attorney K. Joy Mattingly warns that "being off by one day can be fatal to collection." Mail on the 1st, meet no earlier than the 15th. Email counts only for owners who agreed in writing to get notices by email. Everyone else must get a paper notice in the mail.

Check the postmark before the meeting opens

Villa Medici's letter was dated the 10th and postmarked the 18th. Whoever signs the affidavit should look at the postmarked proof of mailing, not the date typed on the letter. If the mailing went out late, send a new notice and move the meeting. That costs about two weeks. The alternative is a judge stopping the assessment.

After the vote, a condo board sends owners a second, separate written notice of the assessment under 718.116(10). It must say exactly what the money is for. Our special assessments guide covers the approval side in depth.

Signing and paying

Pay only for work actually done, confirmed by your own engineer. Hold back 10 percent of each payment (retainage) until the end, and get signed lien releases with every check. A big up-front deposit is the one payment you cannot check against anything.

Before the contract, read your declaration. Look for any cap on assessments and for anything that requires the owners, not just the board, to vote.

Then get competitive bids. The law requires them for any contract over 10 percent of the annual budget, including reserves, in an HOA (720.3055) or 5 percent in a condo (718.3026). The contract itself must be in writing. Engineers, attorneys and managers are exempt from the bid rule.

If a director has any financial tie to a bidder, they must say so in advance. In an HOA that means at least 14 days before the vote (720.3033(6)(b)). The contract then needs a two-thirds vote of the other directors, the disclosure in the minutes, and a report to the owners, who may cancel it.

In a condo the director also leaves the room for the discussion and the vote (718.3027). Finally, check the contractor's license with the DBPR, the state licensing agency.

Hire an engineer for any significant structural, roofing or waterproofing job. The engineer writes the scope, the exact list of work, so every bidder prices the same job. The engineer then inspects the work and signs off on each payment. Without one, you are asking the contractor how much to pay the contractor.

There is a legal bonus too. 617.0830(5) protects directors who rely in good faith on a qualified professional's advice.

Who gets to sign comes from the bylaws and a board vote, not from someone's job title. Before anyone signs, the minutes should name the contractor, the amount and the person authorized to sign. Requiring two signatures on every project check, one of them a director's, is the cheapest control there is.

Be wary of deposits. No law caps them. But 489.126(2) puts a contractor who takes more than 10 percent up front on a clock: apply for any needed permits within 30 days, and start work within 90 days of getting them, unless the association agrees in writing to more time.

Construction attorney Jeffrey Respler of Siegfried Rivera advises payments "commensurate with the percentage of the work that is completed." In plain terms: pay for what is built, as it is built.

Hold back 10 percent of every payment (called retainage) until the job passes final inspection. With each check, collect lien releases: signed forms in which the contractor, and every supplier who sent you a Notice to Owner, confirm they have been paid and give up any claim against the property.

Skip that step and, as Becker's Joseph Adams explains, an unpaid supplier can still come after the association. You pay twice for the same work. See our guides to vendor contracts and concrete restoration.

Try Mosaic alongside your current software. No Risk!

See how Mosaic works
Always Human Support • Florida Built • Easy Cancellation

Change orders

Change orders are how a $1.6 million job becomes $36 million. Neither the condo law nor the HOA law has a rule for them. Your control comes from rules you already follow: the board acts only at noticed meetings, and assessment money is spent on what the notice said.

Decide up front, by board vote, who may approve what, and write that ladder into the contract. For example: the engineer and manager approve small changes inside a set contingency (money set aside for surprises) and report them at the next meeting. Anything bigger goes on a noticed agenda before anyone signs. Record the running total in the minutes.

Money has a ceiling. In a condo, special assessment money may be spent only on the purpose named in the notice (718.116(10)). The HOA statute has no matching sentence, but the notice told owners what the money was for, and your documents and your duty to the owners hold you to it.

Either way, there is only as much money as owners were charged. If the project needs more, or money for a new purpose, that means a new special assessment with a new 14-day notice. Not a quiet change order.

Scope has a ceiling too. A material alteration is a change to the look or use of the common areas, as opposed to a like-for-like repair. In a 2020 condo appeals case, Bailey v. Shelborne, the court held that when owner approval is required for one, it must come "before construction begins." Many HOA declarations say the same.

So a change that turns a repair into an upgrade needs the owner vote first, not after. And if the project's cost has doubled, stop. Have an independent engineer tell you what it will cost to finish before you approve anything else.

What protects directors and managers

Volunteer directors are shielded for good-faith decisions made on professional advice at noticed meetings. The shield has holes exactly where these cases live.

Under 617.0834, a volunteer director cannot be made to pay personally for a board decision, with a few exceptions: the director broke a duty and did so criminally, gained something improper from it, or acted recklessly, in bad faith, or in conscious disregard (knew the rule and ignored it).

A contract with a director's own company is an improper benefit, squarely outside the shield. A deposit paid with no vote at all invites the argument that the director knowingly ignored the association's interest.

Your directors-and-officers (D&O) insurance often excludes these same claims. Read the exclusions before the project starts, not after.

A manager can only do what the board has authorized. Under 468.4334 a manager must account for every dollar of association money. Under 468.436 the state can fine a manager up to $5,000 for each violation of Chapter 718 or 720.

So if you are a manager and someone asks you to pay a deposit before the vote, say no in writing and ask for the minutes that show the vote.

Keep the records and answer requests. Contracts and bids are official records. When an owner asks for them in writing, you have 10 business days. A willful failure after that costs at least $50 a day for up to 10 days, and ignoring a certified-mail request is presumed willful (720.303(5), 718.111(12)(c)).

Villa Medici's fight over records was still going in September 2026, more than a year on. Boards that tell owners more than the law requires rarely get hit with a petition to remove them.

Board checklist

Check off each item as you go. Your checkmarks are saved on this device only.

0 of 10 done

Frequently asked questions

Not in any general way. To ratify means to approve something after the fact, and the statutes give no general path for that. The one exception is for condos: a true emergency item can be taken up by a majority-plus-one vote and then "noticed and ratified at the next regular board meeting" under 718.112(2)(c)1. Otherwise, hold a properly noticed meeting with the contract on the agenda, vote on whether to go ahead or cancel, and record it in the minutes. The officer who signed early may still be personally on the hook if a court finds self-dealing, recklessness or conscious disregard under 617.0834.
Assume you cannot collect it as it stands. Florida association lawyers have called a one-day shortfall "fatal to collection," counting from the day after mailing, and owners can sue to stop collection (Mitchell v. Beach Club of Hallandale, 2009). Start over. Send a new notice with the full 14 days, the purpose and, for a condo, the estimated cost and the contract. File a new affidavit, vote again at an open meeting, then send the written assessment notice.
Florida sets no cap. But a deposit above 10 percent of the contract price triggers 489.126: permits within 30 days, work started within 90 days of the permits. Taking the money and not doing the work, or not refunding it on written demand, is a crime under the same section, and the bigger the amount, the more serious the charge. Lawyers who work with associations recommend a small deposit or none at all, then the payment rules above: pay for certified work, hold back 10 percent, collect lien releases.
Only if the board has actually given that authority, in the management agreement or in a motion recorded in the minutes. Under 468.4334 the manager acts for the association and must account for every dollar. Under 468.436 a manager who breaks Chapter 718 or 720 can lose their license and be fined up to $5,000 per violation. Asked to pay a deposit before the vote? Decline in writing and ask for the minutes.